Chandigarh Trade Link

Sikadur®-32 LP IN

Epoxy structural bonding agent for use at high temperatures

Sikadur®-32 LP IN is a 2-part, epoxy based structural bonding agent for use at high temperatures. It is moisture tolerant and can bond wet or dry materials to damp or dry substrates. Suitable to use in hot and tropical climatic conditions.

Usage

As a structural bonding agent and adhesive for bonding fresh to hardened concrete.

Packaging

1 kg ready to mix unit (Parts A+B)

 

5 kg ready to mix unit (Parts A+B)

 

25 kg ready to mix unit (Parts A+B)

 

Refer to current price list for packaging variations.

Advantages

Colour

Part A

white

Part B

dark grey

Parts A+B mixed

concrete grey

Product Details

CERTIFICATES AND TEST REPORTS


  • CE Marking and Declaration of Performance to EN 1504-4 – Structural bonding

Composition


Epoxy resin and selected fillers

 

Shelf life


24 months from date of production

 

Storage conditions


The product must be stored in original, unopened and undamaged sealed packaging in dry conditions at temperatures between +5°C and +30°C. Always refer to packaging.

 

Density


Mixed resin ~1.4 ± 0,1 kg/l

Value at +23°C.

Compressive strength


Curing time

Curing temperature

 

+23°C

+30°C

+40°C

1 day~2 N/mm2~30 N/mm2
3 days~14 N/mm2~24 N/mm2~41 N/mm2
7 days~34 N/mm2~38 N/mm2~52 N/mm2
14 days~39 N/mm2~43 N/mm2~56  N/mm2

 

 Compressive strength at 4 % elongation

 

Tensile adhesion strength


Curing timeSubstrate

Curing

temperature

Adhesion strength

7 days

Concrete dry

+23°C

> 3 N/mm2 *

7 days

Concrete moist

+23°C

> 3 N/mm2 *

*100% concrete failure

 

Shear adhesion strength


≥ 10 N/mm2 (at 28 days)

(ASTM C882/C882M-20)

 

Shrinkage


Hardens without shrinkage.

Application

Mixing ratio


Part A : Part B = 2 : 1 by weight or volume

 

Layer thickness


~1 mm max.

 

Sag flow


Non-sag up to 1.0 mm thickness on vertical surfaces

(EN 1799)

 

Material temperature


+20°C min. / +40°C max.

 

Ambient air temperature


+20°C min. / +40°C max.

 

Dew point


Beware of condensation.
Steel substrate temperature during application must be at least +3°C above dew point.

 

Substrate temperature


+20°C min. / +40°C max.

 

Substrate moisture content


Cementitious substrates must be dry or matt damp (no standing water).
Brush the adhesive well into the substrate if matt damp.

 

Pot Life


Temperature

Potlife*

Open time

+20°C

~145 minutes

~270 minutes

+30°C

~55 minutes

~240 minutes
+40°C~35 minutes~120 minutes

*200 g

The potlife begins when Parts A+B are mixed. It is shorter at high temperatures and longer at low temperatures. The greater the quantity mixed, the shorter the potlife. To obtain longer workability at high temperatures, the mixed adhesive may be divided into smaller quantities. Another method is to chill Parts A+B before mixing (not below +5 °C).

Consumption


~1.3 kg/m2 per mm of thickness.

This figure is theoretical and does not allow for any additional material due to surface porosity, surface profile, variations in level or wastage etc.

SUBSTRATE QUALITY


Concrete / masonry / mortar / stone

Concrete and mortar must be at least 3–6 weeks old.

Substrate surfaces must be sound, clean, dry or matt damp. Free from standing water, ice, dirt, oil, grease, coatings, laitance, efflorescence, old surface treatments, all loose particles and any other surface contaminants that could affect adhesion of the bonding agent.

Steel

Surfaces must be clean, dry, free from oil, grease, coatings, rust, scale, all loose particles and any other surface contaminants that could affect adhesion of the bonding agent.

 

SUBSTRATE PREPARATION


Concrete / masonry / mortar / stone

Substrates must be prepared mechanically using suitable abrasive blast cleaning, needle gunning, light scabbling, bush hammering, grinding or other suitable equipment to achieve an open textured gripping surface profile.

Steel

Surfaces must be prepared mechanically using suitable abrasive blast cleaning, grinding, rotating wire brush or other suitable equipment to achieve a bright metal finish with a surface profile to satisfy the necessary tensile adhesion strength requirement. Avoid dew point conditions before and during application.

 

All substrates

All dust and loose material must be completely removed from all substrate surfaces before application of the product by vacuum / dust removal equipment.

 

MIXING


Prior to mixing all parts, mix part A (resin) briefly using a mixing spindle attached to a slow speed electric mixer (max. 300 rpm). Add part B (hardener) to part A and mix parts A+B continuously for at least 3 minutes until a uniformly coloured smooth consistency mix has been achieved. To ensure thorough mixing pour materials into a clean container and mix again for approximately 1 minute. Over mixing must be avoided to minimise air entrainment. Mix full units only. Mixing time for A+B = 4,0 minutes. Mix only the quantity which can be used within its pot life.

 

CLEANING OF EQUIPMENT


Clean all tools and application equipment with Sika® Colma Cleaner immediately after use. Hardened material can only be mechanically removed.

Document