Sikafloor®-290 Primer

2-part epoxy resin primer

Solvent-free, two part primer based on epoxy resin.

Usage

As a primer and adhesion promoter on properly prepared:

As a primer for:

Packaging

Pre-batched 28 kg units.
Part A: 8.00 kg container
Part B: 20.0 kg container

Advantages

Colour

Part A – resin:        white liquid
Part B – hardener: yellowish liquid
Mixed colour:        light yellow

Product Details

Shelf Life


Part A, part B: 12 months from date of production
Part C: 9 months from date of production

 

Storage Conditions


The product must be stored in original, unopened and undamaged sealed packaging in dry conditions at temperatures between +5 °C and +35 °C.

 

Density


Part A:          ~ 1.10 kg/l (at +27°C)
Part B:          ~ 1.04kg/l  (at +27°C)
Mixed resin: ~ 1.05 kg/l (at +27°C)

 

Solid Content


~ 28% (by weight)

Tensile Adhesion Strength


> 1.5 N/mm2

(According to ISO 4624)

Application

Mixing Ratio


Part A : Part B = 1 : 2.5 (by weight)

 

Ambient Air Temperature


+10°C min. / +35°C max.

 

Relative Air Humidity


85% r.h. max.

 

Dew Point


Beware of condensation!


The substrate and uncured floor must be at least 3ºC above dew point to reduce the risk of condensation or blooming on the surface of the applied product.

 

Substrate Temperature


+10°C min. / +35°C max.

 

Substrate Moisture Content


≤ 4% moisture content.


Test method: Sika® Tramex moisture meter, CM measurement or Oven-dry method. No rising moisture according to ASTM (PE sheet test).

 

Pot Life


5.6 kg mass

Temperature

Time (at 75% r.h.)

+30°C

~ 45 minutes

Caution:
The end of the product’s potlife is not noticeable! Keep within the limitations mentioned below. Discard material not used within these times.

 

Waiting Time / Overcoating


Before applying Sikafloor®-291 on Sikafloor®-290 Primer allow:

Substrate temperature

Waiting time (Minimum)

Waiting time (Maximum)

+10°C

12 hours

72 hours

+20°C

6 hours

48 hours

+30°C4 hours24 hours

Times are approximate at 75% r.h. and will be affected by changing ambient and substrate conditions, particularly temperature and relative humidity.

 

Applied Product Ready for Use


Substrate temperature

Foot traffic

+10°C

~ 12 hours

+20°C

~ 6 hours

+30°C~ 4 hours

No specific additional curing measures are required.


All times are approximate and will be affected by changing ambient and substrate
conditions

Consumption


0.20 – 0.40 kg/m2/coat.


This figure is theoretical and does not include for any additional material required due to surface porosity, surface profile, variation in level or wastage, etc.

EQUIPMENT


Low speed electric stirrer (~ 300 – 400 rpm) with helical paddle or other suitable equipment.

 

MIXING


Prior to mixing, shake part A and part B briefly until homogenous, then pour both parts into the mixing container and mix thoroughly for 3 minutes until a uniform mix has been achieved.


Pour the mixed material into another container carefully scraping the sides and mixing paddle with a spatula and then mix again briefly to ensure complete and thorough mixing.


Excessive mixing must also be avoided to minimise air entrainment.

 

APPLICATION


Apply Sikafloor®-290 Primer by suitable brush, roller or trowel and overwork with a roller.

 

CLEANING OF TOOLS


Clean all tools and application equipment with water immediately after use. Hardened / cured material can only be removed mechanically.

Document